a company computed the following activity rates using activity - based costing.\nactivity\tactivity rate\nsetup\t$ 2,000 per setup\nmaterials handling\t$ 100 per materials requisition\ninspection\t$ 4 per unit inspected\nthe companys deluxe model used the following activities to produce 2,000 units. compute the overhead cost per unit for the deluxe model using activity - based costing.\nactivity\tactivity rate\nsetup\t6 setups\nmaterials handling\t50 materials requisitions\ninspection\t2,000 units inspected\nmultiple choice\n$6.00.\n$8.50.\n$12.50.
Answer
Explanation:
Step1: Calculate setup cost
$2000\times6 = 12000$
Step2: Calculate materials - handling cost
$100\times50=5000$
Step3: Calculate inspection cost
$4\times2000 = 8000$
Step4: Calculate total overhead cost
$12000 + 5000+8000=25000$
Step5: Calculate overhead cost per unit
$\frac{25000}{2000}=12.5$
Answer:
$12.50$