a company that uses a job order costing system would make the following entry to record the flow of direct…

a company that uses a job order costing system would make the following entry to record the flow of direct materials into production: multiple choice debit work in process inventory, credit cost of goods sold. debit work in process inventory, credit raw materials inventory. debit work in process inventory, credit factory overhead. debit factory overhead, credit raw materials inventory. debit finished goods inventory, credit raw materials inventory.
Answer
Brief Explanations:
In a job - order costing system, when direct materials flow into production, the Work in Process Inventory is debited to increase its balance as it now contains more cost due to the addition of direct materials. The Raw Materials Inventory is credited as the materials are being removed from it for use in production.
Answer:
Debit Work in Process Inventory, credit Raw Materials Inventory.