level scheduling (heijunka)\nassume:\n• one assembly line produces a mix of models and option…

level scheduling (heijunka)\nassume:\n• one assembly line produces a mix of models and option combinations\n• production plan may call for 1500 sunroofs in the coming month\n• assume 25 production days in the coming month, 15 hours of production each day\nwhat is the cycle time needed to achieve the required production of 1500 sunroofs next month?
Answer
Brief Explanations:
A pull process initiates production only in response to a specific customer order.
- A: Frappuccinos are made only when a customer orders them.
- E: Custom burritos are created to individual customer requests.
- F: Bespoke suits are made for specific client measurements/requests. All other options are push processes, where production is done in advance of customer orders based on forecasts or pre-determined demand.
Answer:
A, E, F