multiple choice 1 point which term best represents a significant point or event within a project milestone…

multiple choice 1 point which term best represents a significant point or event within a project milestone task deliverable goal

multiple choice 1 point which term best represents a significant point or event within a project milestone task deliverable goal

Answer

Brief Explanations:

A milestone marks a significant point or event in a project. A task is a single - piece of work, a deliverable is an output of the project, and a goal is the overall aim.

Answer:

A. Milestone