which project is utilizing a predictive approach? a garden area that has a defined space and number of…

which project is utilizing a predictive approach? a garden area that has a defined space and number of plants to be planted, but the time frame of the building of the garden is not set. a building wing where all of the specifications for the classrooms are defined up front and any changes to the specifications have to go through a change control board. a playground with multiple areas, each with its own individual project, with multiple fixed scopes, but the overall project is subject to change. a science lab to where the specifications of the lab can be defined and adjusted once the core of the lab is built.
Answer
Brief Explanations:
A predictive approach in project management is characterized by well - defined upfront requirements. In the case of the building wing, all classroom specifications are defined at the start and changes go through a change control board, which is typical of a predictive approach. The garden has an undefined time frame, the playground has variable overall scope, and the science lab allows for post - core build adjustments, which are not typical of a predictive approach.
Answer:
A building wing where all of the specifications for the classrooms are defined up front and any changes to the specifications have to go through a change control board.