question select the correct answer. which type of feasibility study decides whether new resources and technology are required or if it is possible to use or upgrade existing resources and technology to create the proposed product? operational technical economic schedule

question select the correct answer. which type of feasibility study decides whether new resources and technology are required or if it is possible to use or upgrade existing resources and technology to create the proposed product? operational technical economic schedule

Answer

Brief Explanations:

Technical feasibility assesses if new resources and technology are needed or if existing ones can be used/upgraded to create a product. Operational feasibility focuses on how well the product will fit into operations, economic on cost - benefit, and schedule on time - related aspects.

Answer:

B. technical