a software company working on an international shipping app has been notified that new regulations are in…

a software company working on an international shipping app has been notified that new regulations are in place regarding how privacy for data from the european union is to be handled. conforming to these regulations will cause changes to the project scope. what should a project manager do? gold plate the project inform the shipping company and discuss the changes to be made to the scope inform the shipping company that there will be increased costs for the app inform the shipping company of a delay in the app
Answer
Brief Explanations:
In project management (a subfield of Business, specifically Management), when there are regulatory changes affecting project scope, the project manager should communicate with the client (shipping company) and discuss scope changes. "Gold plating" is unnecessary, and only informing about costs or delays without discussing scope changes is incomplete. Discussing scope changes with the client is the proper approach.
Answer:
The correct option is: "Inform the shipping company and discuss the changes to be made to the scope" (the option with the blue highlight and radio button selected, which is the second option in the list).