tasks assigned tasks completed on time tasks completed late tasks incomplete (past due) chris 24 17 4 3 miguel 29 18 4 7 laura 44 26 16 2 scott 15 13 1 1 if you needed to assign a new task that needs to be completed on time, who would you assign to this task? chris miguel laura scott
Answer
Answer:
D. Scott
Explanation:
Step1: Calculate on - time completion rate for Chris
$\text{On - time rate for Chris}=\frac{17}{24}\approx0.708$
Step2: Calculate on - time completion rate for Miguel
$\text{On - time rate for Miguel}=\frac{18}{29}\approx0.621$
Step3: Calculate on - time completion rate for Laura
$\text{On - time rate for Laura}=\frac{26}{44}\approx0.591$
Step4: Calculate on - time completion rate for Scott
$\text{On - time rate for Scott}=\frac{13}{15}\approx0.867$
Step5: Compare the rates
Since $0.867>0.708 > 0.621>0.591$, Scott has the highest on - time completion rate. So, Scott should be assigned the new task to be completed on time.