drag and drop. identify the best communication methods to use given each situation. a project team checks a…

drag and drop. identify the best communication methods to use given each situation. a project team checks a status board for task progress. a weekly update is sent to team members. a project manager conducts a peer review with a team member.
Answer
Brief Explanations:
- When a project team checks a status - board for task progress, they are retrieving information on their own, so it's a pull communication method.
- Sending a weekly update to team members is pushing information to them, so it's a push communication method.
- A project manager conducting a peer - review with a team member involves two - way communication, so it's an interactive communication method.
Answer:
A project team checks a status board for task progress: Pull A weekly update is sent to team members: Push A project manager conducts a peer review with a team member: Interactive