which of the following is the correct construction project workflow in order from start to finish? a pre…

which of the following is the correct construction project workflow in order from start to finish? a pre - construction, design, construction, procurement, post - construction, conception b conception, pre - construction, design, procurement, construction, post - construction c conception, design, pre - construction, procurement, construction, post - construction d conception, pre - construction, design, construction, procurement, post - construction

which of the following is the correct construction project workflow in order from start to finish? a pre - construction, design, construction, procurement, post - construction, conception b conception, pre - construction, design, procurement, construction, post - construction c conception, design, pre - construction, procurement, construction, post - construction d conception, pre - construction, design, construction, procurement, post - construction

Answer

Brief Explanations:

The project workflow starts with the initial idea or conception. Then comes pre - construction activities like site analysis and permits. After that, the design phase occurs. Procurement of materials and resources follows design, then the actual construction, and finally post - construction activities such as maintenance and evaluation.

Answer:

B. conception, pre - construction, design, procurement, construction, post - construction