osha 10 hour construction: module 10 - demolition exam\nquestion 2 of 10\none of the most important elements…

osha 10 hour construction: module 10 - demolition exam\nquestion 2 of 10\none of the most important elements of the pre - job planning is:\na. to account for the presence of all workers on the job site before detonation\nb. to determine the effect of the demolition on air quality\nc. the location of all utility services\nd. to alert seismologists so they do not get false readings

osha 10 hour construction: module 10 - demolition exam\nquestion 2 of 10\none of the most important elements of the pre - job planning is:\na. to account for the presence of all workers on the job site before detonation\nb. to determine the effect of the demolition on air quality\nc. the location of all utility services\nd. to alert seismologists so they do not get false readings

Answer

Brief Explanations:

Pre - job planning in demolition must identify utility service locations to prevent damage to critical infrastructure like water, gas, and electrical lines during the demolition process. Knowing the presence of workers is important during the demolition phase, air quality impact is more of a monitoring aspect during and after, and alerting seismologists is not a core pre - job planning element.

Answer:

C. The location of all utility services