pmi practice test\n1. which term describes a series of phases that a project passes through from its start…

pmi practice test\n1. which term describes a series of phases that a project passes through from its start to its completion?\n a. project scope\n b. project schedule\n c. project change request\n d. project life cycle\n2. what is the purpose of a project charter?\n a. it formally authorizes the project manager to start the project\n b. it formally authorizes the final project phase\n c. it formally documents all changes to the project scope\n d. it formally defines all project requirements\n3. a project manager is leading a team to build a new community park. what is the project managers primary responsibility?\n a. advertising the new park when it is completed\n b. overseeing the tasks needed to complete the park\n c. getting input from community members about park requirements\n d. designing the playground areas in the park\n4. you are a project manager for a residential construction company. the company offers only three floor - plans for customers to choose from and has built hundreds of these homes. the company assigns you the project of building a new home using one of the floor - plans. in this scenario, why should you choose a predictive project management approach instead of an adaptive one?\n a. the customer predicts to approve every incremental deliverable\n b. the project tasks and activities can be completed in any order\n c. the full scope is known and planned before work begins\n d. continuous changes in scope are expected as work is completed\n5. as a team member on an app development project, you overhear two other team members talk about a website where they illegally copy code from other programmers. according to the project management ethical guidelines, what should you do?\n a. tell the team members that they need to rewrite all the code\n b. wait to see if they copy code again before doing anything\n c. notify the project manager of the situation\n d. email all team members a reminder about plagiarism
Answer
Brief Explanations:
- A project life cycle describes a series of phases a project passes through from start to completion.
- A project charter formally authorizes the project manager to start the project.
- A project manager's primary responsibility is defining project scope.
- A predictive approach is suitable when the full scope is known and planned in advance as in the case of using pre - defined floor plans for home - building.
- According to project management ethical guidelines, one should notify the project manager of the situation of illegal code - copying.
Answer:
- d. Project Life Cycle
- a. It formally authorizes the project manager to start the project
- d. Defining the project scope
- c. The full scope is known and planned in advance
- c. Notify the project manager of the situation