question 2\n1 pts\nwhich technique is not mentioned in the context of handling ambiguity in projects?\nprototypes\nprogressive elaboration\ncontingency reserves\nexperiments

question 2\n1 pts\nwhich technique is not mentioned in the context of handling ambiguity in projects?\nprototypes\nprogressive elaboration\ncontingency reserves\nexperiments

Answer

Brief Explanations:

Prototypes, progressive elaboration, and experiments are common techniques to handle ambiguity in projects. Contingency reserves are mainly for dealing with known - unknown risks in terms of cost and time, not directly related to handling ambiguity.

Answer:

C. Contingency reserves